How long do building permits take in Seattle

Median time from application to issuance or decision, based on public permit records from the last 12 months. Updated July 23, 2026.

Design review
Not enough permits in the last 12 months to publish a number for this phase yet.
Land use
673 days
median
Typically 291 to 918 days
Based on 14 permits
Construction permit
372 days
median
Typically 124 to 454 days
Based on 110 permits

Construction permits by project type

Project typeMedian daysSample size
Multi family372 days85
Retail495 days25
Institutional369 days17
Office181 days15
HotelNot enough data yet6
Sports and recreationNot enough data yet2

Methodology

Measured from a permit application date to its issuance date for construction permits, or its decision date for design review and land use permits. Permits with missing dates, permits reopened after an administrative closure, and permits open longer than 5 years are excluded. A number is only published once at least 8 qualifying permits are available. These are the same permit records visible elsewhere on BuildVue for Seattle, so every number here traces back to a permit a visitor can look up. This page never compares Seattle to another city. Different jurisdictions define application and issuance differently, so a side by side ranking would not be a fair comparison.

Explore Seattle permits on the map

See the individual permits behind these numbers on BuildVue's interactive map.